Victoria Gold: Eagle Mine Construction 90% Complete

Victoria Gold: Eagle Mine Construction 90% Complete

May 7, 2019
Six Ways You Can Manage Home Renovation Stress

Six Ways You Can Manage Home Renovation Stress

December 5, 2020

Will A Chair Lift Singapore Purchase Help

October 31, 2020
Curtain Supplier Singapore Advice For Cleaning Curtains

Curtain Supplier Singapore Advice For Cleaning Curtains

October 31, 2020
4 Key Principles On Hanging Art

4 Key Principles On Hanging Art

October 31, 2020
Choose Appropriate Interior Design Company for Home Interior

Choose Appropriate Interior Design Company for Home Interior

October 23, 2020

Five Expert Tips for Successful Home Loan Application

October 20, 2020

How to Handle Mortgages During the COVID-19 Pandemic

October 13, 2020
Why You Will Need Tree Cutting Services

Why You Will Need Tree Cutting Services

October 6, 2020
Finding The Source Of Pipe Leakages

Finding The Source Of Pipe Leakages

October 6, 2020

Understanding And Handling Pipe Leakages

October 6, 2020
A Beginner Introduction To Pipe Leakages

A Beginner Introduction To Pipe Leakages

October 6, 2020
Getting Waterproofing Painting Help

Getting Waterproofing Painting Help

October 6, 2020
  • Home
  • About Us
  • Anti Spam Policy
  • Contact Us
  • Cookie Policy
  • DMCA
  • Disclaimer
  • Privacy Policy
  • Terms and Conditions
Wednesday, December 23, 2020
  • Login
House Carty
  • Home
  • Real Estate
    • Property Dealers
    • Buying A Property
    • Real Estate Agents
    • Property to Rent
    • Selling Property
    • Property Investment
    • Mortgage
  • Construction
    • Exterior Design
    • Interior Design
  • Home Business
    • Home Improvement
      • Gardening
      • Plumbing
      • Home Decor
        • Painting
        • Furniture
    • Home Inspections
  • Cleaning Services
    • House Cleaning Tips
      • Kitchen
      • Outdoors
      • Roofing
      • Door And Windows
      • Flooring
  • Contact Us
  • Pages
    • Disclaimer
    • Privacy Policy
    • About Us
    • Anti Spam Policy
    • Cookie Policy
    • Terms and Conditions
    • DMCA
No Result
View All Result
House Carty
No Result
View All Result
Home Construction

Victoria Gold: Eagle Mine Construction 90% Complete

by Vicki Horton
May 7, 2019
in Construction
0
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

TORONTO, May 07, 2019 (GLOBE NEWSWIRE) — Victoria Gold Corp. (TSX.V-VIT) (“Victoria” or the “Company”) is pleased to offer an update on construction on the Eagle Gold Mine.

Construction is over ninety% complete with more than 1,250,000 hours labored with out a Lost Time Incident (“LTI”).

“With production sports on the verge crowning glory and operations well advanced, the Eagle Gold Mine is nearing truth,” stated John McConnell, President & CEO. “The mine is beforehand of schedule and equipped to supply first rate fee for all Victoria stakeholders for decades to come.”

 

Current activities on web page are centered on completing mechanical, electric and instrumentation installation on the secondary/tertiary crushing plant and the overland conveyor as well as early pre-commissioning. Photographs and videos of all facilities can be viewed on the Company’s internet-web site (www.Vitgoldcorp.Com).

Construction

Procurement of all foremost device is one hundred% complete with all obese hundreds introduced to website. Overall structural metal is substantively whole, mechanical is about 80% entire whilst electric is seventy five% entire.

Site Infrastructure, consisting of Grid Power

Site infrastructure is complete. The 45km, 69kV powerline from the Yukon electrical grid and the on-website online 13.8 kV electricity distribution are entire. The two associated sub-stations and all transformers are entire. The powerline to website online is about to be energized in early May and might be used for commissioning and into operations.

Crushing & Conveying

The primary crusher install is whole and will be absolutely pre-commissioned with the aid of the vendor, Metso, within the coming days. The MSE retaining wall required for the primary crusher is well ahead of schedule and about 65% entire. The MSE wall is predicted to be complete inside the coming 2-three weeks allowing full commissioning of the primary crusher nicely ahead of time table.

The secondary & tertiary crushing facility structural metallic is substantially whole. Mechanical progress is nearing completion with all important additives anticipated to be absolutely set up inside the coming days. The crew is focused on electrical implementation and the power is on track for an on-time completion.

The overland conveyor, which takes the crushed ore 1.Four kilometers throughout the valley to the heap leach facility, is well ahead of agenda and belting is being installed and spliced. Commissioning of the overland conveyor is scheduled for mid-May. Several other conveyors are nearing of entirety with 3 already pre-commissioned.

Heap Leach Pad & Gold Recovery Plant

The four-layer liner machine and answer piping for the sump of the heap leach pad turned into whole in past due 2018. The event pond is absolutely coated and lining of phase 1 of the heap leach pad above the sump is well superior which gives enough ore capability via 2020 and into 2021. All most important production sports on the gold healing plant are entire and pre-fee is about sixty five% whole.

Commissioning

Commissioning activities are nicely underway. There are 22 primary structures and seventy nine subsystems that have been diagnosed in the commissioning plan with the intention to facilitate early commissioning and a easy commissioning time table. Overall commissioning progress exceeds 10% and large development is expected all through the month of May.

Pre-Production Mining

Development of the primary haul street into the open pit is entire. The first in-pit production bench improvement began in March. To date, pre-manufacturing mining is in advance of schedule and underneath budgeted prices. All work is being self-carried out the usage of the Caterpillar mine fleet which include four 785 haul vans, D10 dozers, a 390 excavator, a 16M grader and a 6040 production shovel.

Operations

Victoria maintains to boost recruitment of the operations crew. The operations control group and key supervisors are in place. The final operations crew are being on-boarded with a modern head be counted of about 164 operations employees. Approximately 45% of the present day team of workers are Yukon residents consisting of several citizens from the First Nation of Nacho Nyak Dun (“FNNND”). We are targeting at the least 50% Yukon residents to fill the approximate 260 employees scheduled to be on board by the quit of 2019.

All main agreement and deliver agreements are in vicinity or are in very last ranges of completion. A enormous range of the providers awarded agreement or supply agreements have partnership preparations with the FNNND Development Corp.

Schedule to First Gold Pour

First ore is expected to be brought to the heap leach pad early in calendar Q3 2019. The Company is presently concentrated on a primary gold pour early in calendar Q4 2019.

Qualified Person
The technical content material of this information release has been reviewed and authorised through Anthony (Tony) George, P.Eng., as the Qualified Person. For additional statistics regarding the Property, refer to the technical report entitled “NI forty three-one zero one Feasibility Study Technical Report for the Eagle Gold Project, Yukon Territory, Canada”, with an powerful date of September 12, 2016, that is available at the Company’s profile at www.Sedar.Com.

About the Dublin Gulch Property
Victoria Gold’s one hundred%-owned Dublin Gulch gold belongings is located in important Yukon Territory, Canada, about 375 kilometers north of the capital town of Whitehorse, and approximately eighty five kilometers from the town of Mayo. The Property is out there via street 12 months-round, and is positioned inside Yukon Energy’s electrical grid.

The Property covers an area of approximately 555 square kilometers, and is the site of the Company’s Eagle Gold Deposit. The Eagle Gold Mine is beneath creation and is anticipated to be Yukon’s subsequent working gold mine. The Eagle and Olive deposits, include Proven and Probable Reserves of 2.7 million oz. Of gold from 123 million tonnes of ore with a grade of zero.Sixty seven grams of gold according to tonne, as outlined in a National Instrument forty three-one zero one feasibility take a look at entitled Report for the Eagle Gold Project and dated October 26, 2016. The NI forty three-one hundred and one Mineral Resource for the Eagle and Olive deposits has been envisioned, as at December five, 2018, to host 208 million tonnes averaging zero.Sixty six grams of gold consistent with tonne, containing 4.Four million oz. Of gold in the “Measured and Indicated” category, consisting of Proven and Probable Reserves, and a in addition 20 million tonnes averaging zero.Sixty four grams of gold consistent with tonne, containing zero.Four million oz of gold inside the “Inferred” class.

Cautionary Language and Forward-Looking Statements
Neither the TSX Venture Exchange, nor its Regulation Services Provider accepts obligation for the adequacy or accuracy of this launch. This press release consists of positive statements that can be deemed “forward-searching statements”. All statements in this discussion, other than statements of historic records, that deal with destiny exploration drilling, exploration activities, expected metal manufacturing, inner rate of go back, envisioned ore grades, graduation of production estimates and projected exploration and capital costs (which include fees and different estimates upon which such projections are based) and events or tendencies that the Company expects, are forward-looking statements. Although the Company believes the expectations expressed in such ahead-searching statements are based on affordable assumptions, such statements are not ensures of destiny performance and real results or tendencies may range materially from those in forward-searching statements. Factors that would reason actual results to vary materially from the ones in ahead-searching statements encompass metallic charges, exploration successes, endured availability of capital and financing, and trendy monetary, marketplace or enterprise situations. Accordingly, readers must not place undue reliance on ahead-looking statements.

ShareTweetPin
Vicki Horton

Vicki Horton

No Result
View All Result

Today Trending

  • Cynthia Beck, Gordon Getty’s Mistress: five Fast Facts You Need to Know

    Cynthia Beck, Gordon Getty’s Mistress: five Fast Facts You Need to Know

    0 shares
    Share 0 Tweet 0
  • Tips for Moving to a New City: A Special Guide for Millennials

    0 shares
    Share 0 Tweet 0
  • Pittsburg residents surprise when production on South Rouse will end

    0 shares
    Share 0 Tweet 0
  • How to Remove Mold From Wood Furniture and Particle Board

    0 shares
    Share 0 Tweet 0
  • Why We Doubt Amy Roloff From ‘Little People, Big World’ Actually Sold Roloff Farms

    0 shares
    Share 0 Tweet 0

Popular Post

Six Ways You Can Manage Home Renovation Stress

Six Ways You Can Manage Home Renovation Stress

December 5, 2020

Will A Chair Lift Singapore Purchase Help

October 31, 2020
Curtain Supplier Singapore Advice For Cleaning Curtains

Curtain Supplier Singapore Advice For Cleaning Curtains

October 31, 2020
House Carty

Copyright © 2020 Housecarty | All Rights Reserved

Navigate Site

  • Home
  • About Us
  • Anti Spam Policy
  • Contact Us
  • Cookie Policy
  • DMCA
  • Disclaimer
  • Privacy Policy
  • Terms and Conditions

Follow Us

No Result
View All Result
  • Home
  • Real Estate
    • Property Dealers
    • Buying A Property
    • Real Estate Agents
    • Property to Rent
    • Selling Property
    • Property Investment
    • Mortgage
  • Construction
    • Exterior Design
    • Interior Design
  • Home Business
    • Home Improvement
      • Gardening
      • Plumbing
      • Home Decor
    • Home Inspections
  • Cleaning Services
    • House Cleaning Tips
      • Kitchen
      • Outdoors
      • Roofing
      • Door And Windows
      • Flooring
  • Contact Us
  • Pages
    • Disclaimer
    • Privacy Policy
    • About Us
    • Anti Spam Policy
    • Cookie Policy
    • Terms and Conditions
    • DMCA

Copyright © 2020 Housecarty | All Rights Reserved

Welcome Back!

Login to your account below

Forgotten Password?

Create New Account!

Fill the forms bellow to register

All fields are required. Log In

Retrieve your password

Please enter your username or email address to reset your password.

Log In